Auckland Battery String Capacity Upgrade

Scheduled Maintenance Report for DataVault

Completed

The scheduled maintenance has been completed.
Posted Nov 27, 2025 - 23:29 NZDT

Update

Project completed without issue
Posted Nov 27, 2025 - 23:28 NZDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 27, 2025 - 10:00 NZDT

Scheduled

We are carrying out work to extend the battery string capacity on all UPS units in our facility. This upgrade increases our overall runtime resilience and supports continued reliability during any power events. No service impact is expected during the work, and our team is closely managing the activity to ensure stable operations throughout. The work is being completed by our UPS partners.
Posted Nov 24, 2025 - 10:01 NZDT
This scheduled maintenance affected: Auckland Data Center (UPS and Power).